Project crashing tradeoff calculator

Calculate solver status for first target and minimum crash cost for first target with your own figures.

Your numbers

Use the units shown. Results update as you change valid inputs.

Use solver status for first target and minimum crash cost for first target to compare changes to your inputs. The method and limits below explain the scope.

Examples

Examples

Try the starting example

Tasks: name, normal duration, minimum duration, crash cost per time unit, prerequisites
A,5,4,10,none B,4,2,5,A
Target project durations to compare
7,8,9
Solver status for first target
optimal
Minimum crash cost for first target
10
Crash reductions by task for first target
A: 0; B: 2
Achieved duration for first target
7
Minimum theoretical project duration
6
Target-duration cost curve
7: 10; 8: 5; 9: 0

Try another scenario

Tasks: name, normal duration, minimum duration, crash cost per time unit, prerequisites
A,5,4,10,none B,4,2,5,A
Target project durations to compare
5,6
Solver status for first target
infeasible
Minimum crash cost for first target
Not applicable
Crash reductions by task for first target
Not applicable
Achieved duration for first target
Not applicable
Minimum theoretical project duration
6
Target-duration cost curve
5: infeasible; 6: 20
Calculation method

Calculation method

Solver status for first target

Enumerate source-to-sink paths and solve a continuous LP imposing enough total duration reduction on every path to meet the first target.

Minimum crash cost for first target

Minimise sum(reduction×supplied crash-unit cost), subject to each task’s reduction bounds.

Crash reductions by task for first target

Return time removed from each task; unavailable if the first target is infeasible.

Achieved duration for first target

Recompute critical-path duration with the returned reduced task durations.

Minimum theoretical project duration

Critical path with every task at its supplied minimum.

Target-duration cost curve

Repeat the LP for each requested target and expose infeasible targets explicitly.

Symbols and units
a
Tasks: name, normal duration, minimum duration, crash cost per time unit, prerequisites
b
Target project durations to compare

Use the units shown. A list keeps the order in which you enter its values. The symbol ^ means “raised to the power of”.

Calculation steps and notation

sum(list) adds all entries in the list.

Assumptions & limits

Assumptions & limits

  • Linear continuous crashing costs, fixed precedence and unlimited resources. Supports at most ten tasks, thirty source-to-sink paths and twenty targets. It does not model discrete acceleration packages, resource contention or nonlinear crash effects.
Are these inputs private?

These calculations run in your browser. A shared link contains the values you choose to share. Only questions submitted to the separate AI finder are sent to OpenAI.

Further reading

YALPS: continuous linear-program constraints and solver statuses ↗